Midway through a major project, your manager informs you that the client has requested significant changes to the requirements. This will invalidate several weeks of your completed work. What is the most productive initial response?
-
A
Acknowledge the change and ask for a meeting to review the new scope, timeline, and resource allocation.
-
B
Inform your manager that the changes are not feasible with the original deadline.
-
C
Continue working based on the original requirements until you receive formal, written documentation.
-
D
Express your frustration about the wasted effort to your team members to build consensus.