In TOGAF, what is the primary purpose of identifying and managing stakeholders in the ADM?
-
A
To assign project tasks to team members
-
B
To ensure that the architecture addresses the concerns of all relevant parties and gains necessary support
-
C
To comply with HR management requirements
-
D
To track project costs by department