What is a dynamic risk assessment, and when might a site supervisor need to carry one out?
Select your answer
A
A risk assessment that is updated annually
B
A continuous, real-time assessment of changing conditions, used when site conditions change unexpectedly and the formal written assessment no longer covers the situation
C
A risk assessment for moving vehicles only
D
A risk assessment completed after an accident