In project scheduling, what is the critical path?
-
A
The sequence of tasks with the highest total cost
-
B
The longest sequence of dependent tasks that determines the shortest project duration
-
C
The set of tasks most likely to experience quality issues
-
D
The list of tasks assigned to the most critical team members