Events and Timeboxes Flashcards
7 cards from real SCRUM practice questions. Tap to flip, then mark Knew It or Still Learning โ missed cards come back until you master them.
Read the first 7 Events and Timeboxes flashcards as text
What is the maximum timebox for the Sprint Planning event in a one-month Sprint?
Answer: Eight hours
Sprint Planning is timeboxed to a maximum of eight hours for a one-month Sprint and is usually shorter for shorter Sprints.
Which event is timeboxed to a maximum of 15 minutes?
Answer: Daily Scrum
The Daily Scrum is a 15-minute timeboxed event for the Developers.
Who is required to attend the Daily Scrum?
Answer: The Developers
The Daily Scrum is an event for the Developers of the Scrum Team.
What is the purpose of the Daily Scrum?
Answer: To inspect progress toward the Sprint Goal and adapt the plan
The Daily Scrum inspects progress toward the Sprint Goal and adapts the Sprint Backlog as needed.
If a Sprint is two weeks long, what is the maximum timebox for the Sprint Retrospective?
Answer: Three hours
The Sprint Retrospective is timeboxed to a maximum of three hours for a one-month Sprint, so it is shorter for a two-week Sprint.
Which event provides the formal opportunity to inspect the Increment with stakeholders?
Answer: Sprint Review
The Sprint Review is where the Scrum Team and stakeholders inspect the outcome of the Sprint.
What is the maximum length of a Sprint in Scrum?
Answer: One month
Sprints are fixed-length events of one month or less.