Construction Management Flashcards
6 cards from real SCE practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 6 Construction Management flashcards as text
What is the work breakdown structure (WBS) in construction management?
Answer: A hierarchical decomposition of the total project scope into manageable work packages
The WBS decomposes the entire project scope into progressively smaller, manageable components (phases → deliverables → work packages → activities), forming the basis for scheduling, costing, and control.
Quality control in construction involves:
Answer: Systematic inspection and testing to verify work meets specifications and standards
Construction QC includes incoming material testing, in-process inspection (rebar placement, concrete pour, compaction), testing (cube tests, soil density), and documentation, all per approved quality plans.
The Gantt chart is used in construction for:
Answer: Visually displaying the project schedule with activity bars against a time axis
Gantt charts show activities as horizontal bars on a time axis, displaying start/finish dates, duration, dependencies, and progress. They are the most common scheduling visualization tool in construction management.
In Saudi construction contracts, a variation order is:
Answer: A formal instruction to change the scope, specification, or timing of contracted work
Variation orders (change orders) formally document changes to the original contract scope, including additions, deletions, or modifications. They must be properly documented and valued per contract provisions.
What is the purpose of a project risk register in construction?
Answer: To identify, assess, and plan responses to potential project risks
A risk register documents identified risks, their probability and impact, risk owners, and planned mitigation/response strategies. In Saudi construction, risks include extreme heat, supply delays, and regulatory changes.
Resource leveling in construction scheduling aims to:
Answer: Smooth out resource demand over time by adjusting non-critical activity timing
Resource leveling uses available float to reschedule non-critical activities, preventing resource peaks and valleys. This reduces mobilization/demobilization costs and improves efficiency.
How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- proscheduler.prometric.com — Eligibility, retake policy · verified Nov 2026
- prometric.com — Test delivery · verified Nov 2026