What distinguishes a 'stretch objective' from a committed objective in PI Planning?
-
A
Stretch objectives are assigned by Product Management only
-
B
Stretch objectives are not counted in PI Predictability if missed
-
C
Stretch objectives are mandatory but lower priority
-
D
Stretch objectives replace risks on the program board