SA SAFe Agilist Program Execution & Delivery 2 — Questions and Answers
Question 1: Which ceremony is specifically designed to synchronize all Agile teams on a train and identify cross-team dependencies during a PI?
- Daily Scrum
- Scrum of Scrums (Correct answer)
- System Demo
- Sprint Review
Correct answer: Scrum of Scrums
The Scrum of Scrums is an ART-level synchronization event where team representatives identify and resolve cross-team impediments and dependencies.
Question 2: What is the recommended WIP limit approach for a Kanban system used in SAFe?
- Set WIP limits based on team velocity
- Pull new work only when capacity is available (Correct answer)
- Prioritize work by business value before pulling
- Assign WIP limits per team member
Correct answer: Pull new work only when capacity is available
Kanban systems use pull-based WIP limits so new work is only started when current work is completed, preventing overloading.
Question 3: During PI Planning, who is primarily responsible for presenting the vision and top 10 features to the teams?
- Release Train Engineer
- Scrum Master
- Business Owner
- Product Management (Correct answer)
Correct answer: Product Management
Product Management owns and presents the program vision along with the top features for the upcoming PI during the PI Planning event.
Question 4: What does a red flag on a program board during PI Planning signify?
- A completed dependency
- An unresolved dependency or risk (Correct answer)
- A team that is over-committed
- A stretch objective
Correct answer: An unresolved dependency or risk
Red strings or flags on the program board indicate dependencies that are at risk or have not been agreed upon between teams.
Question 5: Which metric best reflects the predictability of an Agile Release Train?
- Team velocity average
- PI Predictability Measure (Correct answer)
- Number of defects per sprint
- Cumulative flow throughput
Correct answer: PI Predictability Measure
The PI Predictability Measure tracks the percentage of planned Business Objectives actually achieved, reflecting how reliably the ART delivers value.
Question 6: In SAFe, what is the primary purpose of the Inspect & Adapt event?
- Showcase team features to customers
- Plan the next PI's objectives
- Identify and commit to improvement stories (Correct answer)
- Reprioritize the Program Backlog
Correct answer: Identify and commit to improvement stories
The Inspect & Adapt event ends the PI with a structured problem-solving workshop that results in improvement stories added to the next PI backlog.
Question 7: When a team consistently fails to meet sprint goals due to unplanned work, which SAFe practice most directly addresses this?
- Increasing team capacity
- Adding more story points to planning
- Maintaining an Innovation & Planning (IP) iteration buffer (Correct answer)
- Escalating to the Release Train Engineer
Correct answer: Maintaining an Innovation & Planning (IP) iteration buffer
The IP Iteration provides buffer capacity to handle unplanned work, technical debt, and exploration without disrupting committed iterations.
Which ceremony is specifically designed to synchronize all Agile teams on a train and identify cross-team dependencies during a PI?