In SAFe, what does a widening 'Work in Process' band on a cumulative flow diagram indicate?
-
A
The team is accelerating delivery effectively
-
B
Inventory is building up โ more work is entering than leaving the system
-
C
The ART has successfully expanded its capacity
-
D
Teams are pulling more work to maintain steady velocity