SAFe Agilist Program Execution & Delivery Flashcards
7 cards from real SA practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 7 SAFe Agilist Program Execution & Delivery flashcards as text
What is the primary purpose of a 'Definition of Done' (DoD) in SAFe program execution?
Answer: To establish a shared quality agreement for when work is truly complete
The DoD is a team-level agreement specifying all quality criteria that must be met before a story or feature can be considered complete, preventing technical debt accumulation.
During PI Execution, which practice helps teams visualize the flow of work and identify bottlenecks?
Answer: Cumulative Flow Diagrams (CFDs)
Cumulative Flow Diagrams visualize work across Kanban states over time, making bottlenecks and flow inefficiencies visible to the team.
An ART's System Demo reveals significant integration issues across teams. Which action BEST aligns with SAFe principles?
Answer: Use the I&A problem-solving workshop to identify root causes and improvements
The Inspect & Adapt event's structured problem-solving workshop is SAFe's designated mechanism for addressing systemic ART-level issues discovered during execution.
In SAFe, what does the term 'Takt time' refer to in the context of value stream flow?
Answer: The rate at which customers demand value from the system
Takt time is a Lean concept representing the rate of customer demand; optimizing flow to match Takt time ensures value delivery without overproduction.
Which of the following is an example of an Agile Release Train (ART) anti-pattern?
Answer: Multiple teams using different iteration lengths within the same ART
All teams on an ART must use the same iteration cadence; mismatched iteration lengths break synchronization and make cross-team coordination nearly impossible.
What is the recommended action when a team's velocity is consistently lower than planned during a PI?
Answer: Adjust velocity-based planning assumptions and investigate root causes
Sustainable improvement requires understanding why velocity is lower and adjusting future planning assumptions accordingly, rather than reactive resourcing changes.
Which SAFe event specifically produces a set of improvement stories that are added to the next PI's backlog?
Answer: Inspect & Adapt
The Inspect & Adapt event's problem-solving workshop concludes with improvement stories that are prioritized and entered into the following PI's planning backlog.
How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- support.scaledagile.com — Test delivery, retake fee, renewal, score validity, fees, exam information · verified Oct 2026
- scaledagile.com — Eligibility, passing score, time limit · verified Oct 2026