SAFe Agilist Program Execution & Delivery Flashcards
7 cards from real SA practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 7 SAFe Agilist Program Execution & Delivery flashcards as text
What distinguishes a 'stretch objective' from a committed objective in PI Planning?
Answer: Stretch objectives are not counted in PI Predictability if missed
Stretch objectives represent optional goals teams pull in if capacity allows; missing them does not negatively impact PI Predictability scores.
Which role facilitates the ART-level process and ensures teams follow SAFe practices during program execution?
Answer: Release Train Engineer
The Release Train Engineer (RTE) is the servant leader and coach for the ART, responsible for facilitating events and removing impediments at the program level.
A team discovers mid-sprint that a feature dependency on another team will not be delivered on time. What is the BEST immediate action?
Answer: Raise the dependency in the Scrum of Scrums
The Scrum of Scrums is the proper ART synchronization forum for surfacing and resolving cross-team dependency issues quickly.
What is the typical timebox for a SAFe sprint (iteration)?
Answer: 2 weeks
SAFe recommends a fixed 2-week iteration cadence to create a predictable heartbeat for development teams across the ART.
How does SAFe handle technical debt during Program Execution?
Answer: Teams allocate 20% capacity each iteration to debt reduction
SAFe recommends teams reserve approximately 20% of iteration capacity to address technical debt and keep the system healthy throughout execution.
Which artifact captures the team's plan for a sprint, including stories and their acceptance criteria?
Answer: Iteration Plan
The Iteration Plan is the team-level commitment for a sprint, listing the stories selected from the Team Backlog along with acceptance criteria and tasks.
What is the recommended frequency for the ART Sync event in SAFe?
Answer: Weekly
The ART Sync (including Scrum of Scrums and PO Sync) is typically held weekly to maintain alignment across teams between PI Planning events.
How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- support.scaledagile.com — Test delivery, retake fee, renewal, score validity, fees, exam information · verified Oct 2026
- scaledagile.com — Eligibility, passing score, time limit · verified Oct 2026