What is the purpose of the PO Sync meeting during ART execution?
-
A
To assign developers to user stories
-
B
To align Product Owners across the ART on feature progress, priorities, and cross-team dependencies
-
C
To review test results from the previous sprint
-
D
To finalize the release plan for the next PI