← All 403A Flashcard Decks

Formwork Flashcards

6 cards from real 403A practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 6 Formwork flashcards as text
  1. What is the primary purpose of formwork in concrete construction?

    Answer: To shape and support wet concrete until it gains sufficient strength

    Formwork is a temporary mould used to shape and support wet (plastic) concrete until it hardens and gains sufficient strength to support its own weight and applied loads. It defines the shape, size, and surface finish of the concrete element.

  2. What is the maximum recommended rate of concrete pour for wall forms to minimize lateral pressure?

    Answer: 1.0 m per hour

    A common recommended pour rate for wall forms is approximately 1.0 m per hour, which allows the concrete at the bottom to begin setting and reduces the maximum lateral pressure on the forms. Higher pour rates require stronger formwork.

  3. What is the purpose of form ties (snap ties) in wall formwork?

    Answer: To hold opposing form walls at the correct spacing and resist concrete pressure

    Form ties (snap ties) extend through the wall thickness to hold the two opposing form faces at the correct spacing while resisting the lateral pressure exerted by the wet concrete. They break off at the form face after stripping.

  4. When is it generally safe to strip wall formwork for a standard residential foundation in moderate Canadian temperatures?

    Answer: 24 to 48 hours after pouring

    Wall formwork can typically be stripped 24 to 48 hours after pouring in moderate temperatures (above 10°C), as the concrete will have gained enough strength to be self-supporting. Cold weather may require longer curing times before stripping.

  5. What is a keyway in footing formwork?

    Answer: A groove formed in the top of a footing to interlock with the foundation wall above

    A keyway is a continuous groove formed in the top surface of a concrete footing. When the foundation wall is poured on top, concrete fills the keyway, creating a mechanical interlock that resists lateral movement.

  6. What type of release agent is applied to formwork before placing concrete?

    Answer: Form oil or release agent to prevent concrete from bonding to the forms

    Form oil or release agent is applied to the form surfaces before concrete is placed. It prevents the concrete from bonding to the forms, allowing clean stripping and extending the life of the formwork materials.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. red-seal.ca — Exam format, passing score, time limit · verified Oct 2026
  2. skilledtradesontario.ca — Eligibility, renewal, test delivery, fees, retake policy, retake fee · verified Oct 2026