Concrete Formwork Flashcards
6 cards from real 403A practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 6 Concrete Formwork flashcards as text
What is a waler (wailer) in wall formwork and what does it do?
Answer: A horizontal member running along the form face to distribute tie loads and stiffen the form panels
Walers are horizontal members (typically doubled 38×89 mm lumber) running along the outside face of form panels. They span between form ties, distribute the concentrated tie loads across the panel face, and prevent the panels from bowing between ties.
What is the minimum concrete cover required over steel reinforcing bars for a foundation wall exposed to soil in Canada per CSA A23.1?
Answer: 60 mm
CSA A23.1 requires a minimum cover of 60 mm for concrete cast against and permanently exposed to earth (such as foundation walls). This protects the steel from corrosion-causing moisture and soil chemicals.
What is the purpose of vibrating fresh concrete after it is placed in formwork?
Answer: To consolidate the concrete, eliminate voids and air pockets, and ensure it flows around reinforcing steel
Internal vibrators consolidate concrete by temporarily liquefying it, allowing air pockets and voids to escape and ensuring complete contact with form surfaces and encapsulation of reinforcing steel. Over-vibration can cause segregation.
What is bleed water in fresh concrete and why is it a concern for surface finishing?
Answer: Water that migrates to the surface as concrete settles — finishing too early traps it and weakens the surface
Bleed water rises to the surface as the denser concrete particles settle. If finishers work the surface before bleed water evaporates, they drive water back into the top layer, increasing the water-cement ratio and creating a weak, dusty surface layer (surface scaling).
What is the purpose of a construction joint in a concrete pour?
Answer: A planned stopping point in a pour where fresh concrete will later be bonded to the hardened face
Construction joints are planned stoppage points where a pour ends and a subsequent pour begins. The hardened surface must be prepared (cleaned, roughened, and often treated with bonding agent or fresh concrete) to ensure proper bond with the next pour.
When stripping (removing) wall forms after a concrete pour, what is the minimum concrete strength typically required before formwork is removed?
Answer: Approximately 3.5 MPa (sufficient to resist damage from stripping forces)
Forms may be stripped once the concrete can support its own weight and resist damage from the stripping operation — typically around 3.5 MPa. This usually occurs within 24-48 hours depending on temperature and mix. Full design strength takes 28 days.
How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- red-seal.ca — Exam format, passing score, time limit · verified Oct 2026
- skilledtradesontario.ca — Eligibility, renewal, test delivery, fees, retake policy, retake fee · verified Oct 2026