A case study describes an existing building where horizontal cable runs must pass through a 2-hour fire-rated wall. What is the correct approach per applicable codes?
-
A
Use plenum-rated cable, which is exempt from firestop requirements
-
B
Install all cables in a single conduit and apply a UL-listed firestop system around the conduit
-
C
Route cables through HVAC ductwork to avoid penetrating the fire wall
-
D
Apply fire-rated paint on cables within 1 m of the penetration