A maintenance technician has four work orders due today: (1) a leaking hydraulic line on a press running at 40% capacity, (2) a burned-out overhead light in a storage room, (3) a conveyor belt that makes noise but runs normally, and (4) an air compressor whose pressure relief valve chattered once but hasn't repeated. Which sequence best reflects industrial time-management principles?
-
A
1 → 3 → 4 → 2
-
B
1 → 4 → 3 → 2
-
C
3 → 1 → 2 → 4
-
D
2 → 1 → 4 → 3