A maintenance technician has three simultaneous work orders: a conveyor bearing showing early-stage wear (non-critical line), a hydraulic leak on a press that is slowing—but not stopping—production by 15%, and a PM inspection due today on a critical air compressor that feeds three downstream lines. Production scheduling has 45 minutes of planned downtime on the press starting in 2 hours. What is the MOST efficient sequencing of these tasks?
-
A
Perform the PM inspection first, then address the hydraulic leak during the planned downtime window, then schedule the bearing replacement
-
B
Fix the hydraulic leak immediately to restore full press speed, then do the PM inspection, then order parts for the bearing
-
C
Combine the hydraulic leak repair with the planned downtime window, complete the PM inspection now, then schedule the bearing for the next shift
-
D
Defer all three tasks and present them at the daily maintenance meeting for priority assignment by the supervisor