A maintenance technician has four pending work orders: a conveyor bearing replacement (4 hrs, production impact if delayed >2 hrs), a lighting fixture swap (30 min, no production impact), an air compressor PM (2 hrs, due in 6 hrs), and a hydraulic leak repair (1.5 hrs, slow leak with 8-hr safe window). Using critical-path prioritization, what is the CORRECT sequence?