During a pit inspection, a QEI notes a permanently installed ladder. According to ASME A17.1, what is the minimum required horizontal distance between the ladder rungs and the nearest permanent object behind the ladder?
Answer: 4.5 inches
ASME A17.1 requires a clear distance of not less than 4.5 inches from the ladder rungs to the nearest permanent object behind the ladder to ensure adequate footing for personnel.
While inspecting a newly installed elevator pit, you find a single duplex receptacle. Which of the following is a critical requirement for this receptacle according to the National Electrical Code (NEC)?
Answer: It must have Ground-Fault Circuit-Interrupter (GFCI) protection.
NEC 620.24 requires that at least one 125-volt, single-phase, duplex receptacle in the pit be GFCI-protected for personnel safety. The pit lighting and receptacle must be on a separate branch circuit, and the lighting cannot be on the load side of the GFCI.
An inspector is verifying hoistway door clearances on an elevator with swinging doors installed under ASME A17.1-2016. What is the maximum permitted clearance between the hoistway side of the landing door and the edge of the landing sill?
Answer: 3/4 inch (19 mm)
For swinging doors, the ASME A17.1-2016 code, Section 5.3, mandates that the clearance between the hoistway side of the landing door and the landing sill edge shall not exceed 3/4 inch (19 mm).
A QEI is performing an inspection in a building where Firefighters' Emergency Operation is provided. What is the minimum pumping capacity required for the sump pump in the elevator pit?
Answer: 3,000 gallons per hour
ASME A17.1, Rule 2.2.2.5, specifies that for elevators with Firefighters' Emergency Operation, a drain or sump pump must be provided with the capacity to remove a minimum of 3,000 gallons per hour per elevator.
Which of the following is generally prohibited from being installed inside an elevator hoistway, unless it is for the exclusive use of the elevator?
Answer: Steam pipes for building heat
ASME A17.1 generally prohibits pipes, ducts, and wiring that are not used directly in connection with the elevator from being installed in the hoistway. Steam pipes present a particular danger due to the risk of discharge and heat affecting elevator operation and safety.
During a pit inspection, the inspector must verify the condition and presence of required equipment. Which of the following is NOT a standard component an inspector would typically verify is present and in good condition within the pit?
Answer: Counterweight sheave
The counterweight sheave is typically located at the top of the hoistway or on the counterweight frame itself, not in the pit. The inspector would find the car buffer(s), pit stop switch, and often the governor rope tension sheave assembly within the pit area.
How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- naesai.org — Renewal, test delivery, eligibility, fees, retake fee · verified Nov 2026
- dropbox.com — Exam format, passing score, registration deadline, retake policy, score release, time limit · verified Nov 2026