A method statement requires workers to operate within 1 meter of an open line. Visibility is reduced to less than the required warning distance due to fog. What should the PICOP do?
-
A
Allow work to continue because reduced visibility affects trains equally
-
B
Suspend work until visibility is sufficient to provide the required warning time
-
C
Double the number of lookouts to compensate for poor visibility
-
D
Reduce the distance at which workers stand from the open line