When conducting a dynamic risk assessment on track, which factor should MOST immediately cause you to stop work and reassess?
-
A
The scheduled train frequency increases by one service per hour
-
B
A line speed change is implemented that was not identified in the original method statement
-
C
The site supervisor takes a scheduled break
-
D
Your PPE becomes slightly uncomfortable due to temperature