A COSS is about to start work but the planned protection method has become unavailable. What is the correct course of action?
-
A
Implement the next available protection method and inform the group
-
B
Stop work, do not allow the group onto the line, and escalate to the PICOP
-
C
Use a temporary lookout arrangement until the original method is restored
-
D
Proceed with reduced staff numbers to lower risk exposure