PTS - Personal Track Safety Risk Assessment and Method Statements Flashcards

6 cards from real PTS practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 6 PTS - Personal Track Safety Risk Assessment and Method Statements flashcards as text
  1. What is 'residual risk' in the context of a risk assessment?

    Answer: The risk that remains after all control measures have been applied

    Residual risk is the level of risk that remains after all practicable control measures have been put in place.

  2. When should a risk assessment be reviewed and updated?

    Answer: Regularly and whenever there is a significant change to the work or conditions

    Risk assessments must be reviewed regularly and updated whenever the task, workforce, environment, or working conditions change significantly.

  3. Which of the following is NOT typically a hazard addressed in a PTS risk assessment?

    Answer: Office workstation ergonomics

    Office workstation ergonomics is not relevant to a PTS risk assessment, which focuses on hazards specific to working on or near railway tracks.

  4. What does 'likelihood' refer to when evaluating a hazard in a risk assessment?

    Answer: The probability that a hazard will result in harm

    Likelihood refers to the probability or chance that a particular hazard will actually result in harm to a worker.

  5. When must a dynamic risk assessment be carried out?

    Answer: When unexpected hazards arise during work that were not in the original assessment

    A dynamic risk assessment is carried out on the spot when unexpected hazards arise that were not identified in the original risk assessment.

  6. What is the significance of a 'significant finding' in a risk assessment?

    Answer: It identifies a hazard requiring a specific control measure to reduce risk to an acceptable level

    A significant finding identifies a hazard that poses enough risk to require a documented control measure to reduce it to an acceptable level.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. nsar.co.uk — Test delivery, time limit, renewal · verified Oct 2026
  2. info.railsentinel.co.uk — Fees, eligibility · verified Oct 2026
PTS - Personal Track Safety Risk Assessment and Method Statements Flashcards — PTS Study Cards with Answers