A project manager calculates the Cost Performance Index (CPI) as 0.85. What does this indicate?
-
A
The project is 15% under budget
-
B
The project is getting $0.85 in value for every $1 spent
-
C
The project will finish 15% ahead of schedule
-
D
The project has 85% of its budget remaining