Risk Monitoring and Control Flashcards
7 cards from real Project Risk Management practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 7 Risk Monitoring and Control flashcards as text
What role does a 'risk owner' play specifically during the Monitor Risks process?
Answer: Monitors assigned risks, implements responses, and reports status
During monitoring, each risk owner is responsible for watching their assigned risks, executing planned responses when triggers occur, and reporting current status to the project manager.
Which of the following best explains why risk monitoring must be continuous rather than a single event?
Answer: Project conditions change, new risks emerge, and existing risks evolve throughout the project
Projects are dynamic; new risks can emerge at any phase, existing risks can escalate or diminish, and project conditions change—making continuous monitoring essential for effective risk management.
A risk audit reveals that risk responses are not being consistently implemented. What is the most appropriate corrective action?
Answer: Issue change requests to update the risk management plan and reinforce accountability
When audits reveal implementation gaps, the project manager should issue change requests to address the root cause and strengthen accountability through updated plans and clearer ownership.
In a risk register, what does it mean when a risk's 'risk score' increases during a monitoring review?
Answer: The combination of probability and/or impact has grown, increasing the risk's priority
An increasing risk score (probability × impact) means the risk has become more likely or more severe, requiring elevated attention and potentially revised response strategies.
Which of the following is a key difference between monitoring risks and controlling risks?
Answer: Monitoring tracks risk status; controlling implements responses and adjustments
While often combined as 'Monitor and Control Risks,' monitoring refers to tracking risk status and triggers, while controlling involves implementing responses and adjusting plans based on what is observed.
A project manager notices that contingency reserves are being consumed faster than expected relative to project progress. What risk monitoring action should follow?
Answer: Perform a reserve analysis and reassess outstanding risks
Faster-than-expected reserve consumption signals that risks may be occurring more frequently or severely than planned, warranting an immediate reserve analysis and risk reassessment.
Which document is updated as a key output of the Monitor Risks process to capture lessons about risk management effectiveness?
Answer: Lessons learned register
The lessons learned register captures insights about what risk monitoring and control approaches worked or failed, providing valuable guidance for future phases and projects.
How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- pmi.org — Passing score, score release, test dates, renewal, fees, score validity, exam format, retake policy · verified Oct 2026
- pearsonvue.com — Test delivery · verified Oct 2026