Risk Monitoring and Control Flashcards
7 cards from real Project Risk Management practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 7 Risk Monitoring and Control flashcards as text
What is the difference between a 'residual risk' and a 'secondary risk'?
Answer: Residual risks remain after responses; secondary risks are created by responses
Residual risks are smaller risks that remain after a response is applied, while secondary risks are new risks introduced as a direct result of implementing a risk response.
A project's risk exposure has significantly increased due to scope changes. Which action should the project manager take?
Answer: Perform an unscheduled risk reassessment immediately
Significant changes like scope additions warrant immediate, unscheduled risk reassessments to ensure the risk management plan reflects current project realities.
Which output of the Monitor Risks process can result in change requests to the project management plan?
Answer: Recommended corrective or preventive actions
Recommended corrective actions (to deal with occurred risks) and preventive actions (to reduce future risk probability) can trigger formal change requests to the project management plan.
A risk owner reports that the probability of a high-priority risk has decreased significantly. What should the project manager update?
Answer: The risk register with new probability and priority ranking
When risk parameters change, the risk register must be updated to reflect the new probability, impact, and resulting priority to ensure accurate monitoring.
What does 'variance and trend analysis' help a project manager understand during risk monitoring?
Answer: Whether project performance deviations indicate emerging risks
Variance and trend analysis examines project performance data over time to identify trends that might indicate emerging risks or signal that existing risks are materializing.
In risk monitoring, 'risk reassessment' differs from 'risk audits' in that:
Answer: Reassessment identifies new risks and re-evaluates existing ones; audits evaluate the effectiveness of risk processes
Risk reassessment focuses on identifying new risks and re-evaluating existing risk rankings, while risk audits examine whether risk management processes and responses are being executed effectively.
Which of the following is NOT typically an input to the Monitor Risks process?
Answer: Project scope statement (initial)
The initial project scope statement is not a direct input to Monitor Risks; rather, work performance data, the risk register, and the risk management plan are the key inputs.
How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- pmi.org — Passing score, score release, test dates, renewal, fees, score validity, exam format, retake policy · verified Oct 2026
- pearsonvue.com — Test delivery · verified Oct 2026