Which tool is primarily used to track the status of identified risks and monitor residual risks throughout the project?
Answer: Risk register
The risk register is the primary document for tracking identified risks, responses, owners, and current status throughout the project lifecycle.
A project manager discovers a risk that was not identified during initial planning. What should be done first?
Answer: Add it to the risk register and analyze it
Newly identified risks should be added to the risk register and then analyzed for probability and impact before determining a response.
What is a 'risk trigger' in the context of risk monitoring and control?
Answer: An indicator that a risk is about to occur
A risk trigger (also called a warning sign or symptom) is an event or condition that indicates a risk is about to occur or has occurred.
Which of the following best describes 'workarounds' in risk monitoring?
Answer: Unplanned responses to risks that were not anticipated or mitigated
Workarounds are unplanned responses developed on the spot when a risk occurs that was either not identified or had no planned response.
During a risk audit, the project team evaluates the effectiveness of risk responses. Who typically facilitates this audit?
Answer: An independent auditor or the project manager
Risk audits can be facilitated by the project manager or an independent auditor to objectively evaluate how well risk responses have worked.
What is the primary purpose of reserve analysis during the Monitor Risks process?
Answer: To compare remaining contingency reserves to remaining risk exposure
Reserve analysis during monitoring compares the amount of contingency reserves remaining against the level of remaining risk to ensure adequate coverage.
Which metric indicates that risk monitoring activities are being performed effectively on a project?
Answer: Risk responses are implemented on time and secondary risks are tracked
Effective risk monitoring is demonstrated when responses are implemented as planned and secondary risks (resulting from responses) are identified and tracked.
How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- pmi.org — Passing score, score release, test dates, renewal, fees, score validity, exam format, retake policy · verified Oct 2026
- pearsonvue.com — Test delivery · verified Oct 2026