Which risk response strategy involves shifting the negative impact of a risk to a third party?
Answer: Transfer
Transfer shifts the financial or operational impact of a risk to another party, such as through insurance or outsourcing.
A project team identifies that a vendor delay could push the schedule out by two weeks. They add an extra two weeks to the project plan. This is an example of:
Answer: Contingency reserve
Contingency reserves are buffer time or budget added to account for identified risks that may occur.
Which tool is used to prioritize risks based on their probability and impact?
Answer: Probability and impact matrix
A probability and impact matrix maps risks on a grid to classify them as high, medium, or low priority.
What does 'residual risk' refer to in project risk management?
Answer: Risk remaining after responses have been implemented
Residual risk is the risk that remains after planned risk responses have been applied.
During which process is the Risk Management Plan created?
Answer: Plan Risk Management
Plan Risk Management is the process that defines how risk management activities will be conducted throughout the project.
A project manager wants to exploit a positive risk. Which of the following actions best describes exploitation?
Answer: Ensuring the opportunity definitely occurs
Exploiting a positive risk means taking actions to ensure the opportunity definitely happens.
Which of the following is an example of a secondary risk?
Answer: A new risk that arises as a result of implementing a risk response
Secondary risks are new risks that emerge as a direct consequence of executing a risk response action.
How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- pmi.org — Passing score, score release, test dates, renewal, fees, score validity, exam format, retake policy · verified Oct 2026
- pearsonvue.com — Test delivery · verified Oct 2026