Mixed Deck — All Project Risk Management Topics Flashcards
100 cards from real Project Risk Management practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 20 Mixed Deck — All Project Risk Management Topics flashcards as text
A risk owner's primary communication responsibility is to:
Answer: Provide regular status updates on assigned risks and response effectiveness
Risk owners must keep the project team and manager informed about the current status, triggers, and effectiveness of responses for their assigned risks.
Which of the following best describes the "Share" risk response strategy for opportunities?
Answer: Forming a joint venture or partnership to capitalize on an opportunity that the project cannot capture on its own.
The "Share" strategy for positive risks (opportunities) involves allocating some or all of the ownership of the opportunity to a third party who is best able to capture the benefit for the project. A joint venture is a classic example of this. Paying a premium for a threat is "Transfer". Increasing the probability is "Enhance," and ensuring it happens is "Exploit."
You discover a risk has a 25% chance of happening in any month of a project with an eight-month length during the Perform Qualitative Risk Analysis phase. A contingency reserve of 8% of the project budget has been set aside, and the project's cost performance index is 0.7. What is the likelihood that the risk will materialize in the sixth month?
Answer: 25%
Explanation: There is a 25% possibility that the risk will materialize each month. The further information in the query is not pertinent.
How do Project Risk Management professionals establish measurable quality objectives?
Answer: By defining specific, measurable, achievable, relevant, and time-bound quality targets
This is fundamental to Project Risk Management practice. By defining specific, measurable, achievable, relevant, and time-bound quality targets represents the professional standard for quality in the Project Risk Management certification framework.
Which approach best demonstrates professional competency in Project Risk Management practice?
Answer: Integrating continuing education, practical experience, and evidence-based decision making
This is fundamental to Project Risk Management practice. Integrating continuing education, practical experience, and evidence-based decision making represents the professional standard for professional standards in the Project Risk Management certification framework.
Which of the following is NOT typically an input to the Monitor Risks process?
Answer: Project scope statement (initial)
The initial project scope statement is not a direct input to Monitor Risks; rather, work performance data, the risk register, and the risk management plan are the key inputs.
In quantitative risk analysis, which technique determines which risks have the most potential impact on project objectives?
Answer: Sensitivity analysis
Sensitivity analysis (often shown as a tornado diagram) identifies which variables have the greatest effect on project outcomes.
Which of the following claims about risk management is accurate?
Answer: Risk register documents all the risks (positive or negative) in detail
The risk register is a comprehensive document that serves as a central repository for all identified risks throughout the project lifecycle. It details both threats (negative risks) and opportunities (positive risks), including their descriptions, causes, potential impacts, probabilities, owners, and planned responses. This ensures all risk information is documented and managed effectively.
During which process is the Risk Management Plan created?
Answer: Plan Risk Management
Plan Risk Management is the process that defines how risk management activities will be conducted throughout the project.
How do Project Risk Management professionals maintain digital competency?
Answer: Through ongoing training, practice with new tools, and staying current with technological advances
This is fundamental to Project Risk Management practice. Through ongoing training, practice with new tools, and staying current with technological advances represents the professional standard for technology in the Project Risk Management certification framework.
A project manager learns a key vendor is experiencing significant financial difficulties. Which risk response is most appropriate?
Answer: Develop a contingency plan including an alternative qualified vendor
Developing a contingency plan with an alternative vendor is a proactive response that ensures project continuity if the primary vendor becomes unable to deliver.
Which of the following is a primary objective of performing a risk reassessment during the Monitor Risks process?
Answer: To identify new risks, re-evaluate existing ones, and close outdated risks.
Risk reassessment is a key activity in risk monitoring that involves regularly reviewing the risk register to identify any new risks, reassessing the probability and impact of current risks, and closing risks that are no longer relevant to the project.
What is the significance of a code of conduct for Project Risk Management professionals?
Answer: It establishes expected behaviors and ethical standards that protect the public and profession
This is fundamental to Project Risk Management practice. It establishes expected behaviors and ethical standards that protect the public and profession represents the professional standard for professional standards in the Project Risk Management certification framework.
A project team allocates budget to cover the cost of accepted risks if they occur. This budget is called:
Answer: Contingency reserve
Contingency reserve is set aside to address known risks (known unknowns) that may occur during the project.
During a risk audit, the project team evaluates the effectiveness of risk responses. Who typically facilitates this audit?
Answer: An independent auditor or the project manager
Risk audits can be facilitated by the project manager or an independent auditor to objectively evaluate how well risk responses have worked.
Which tool is primarily used to track the status of identified risks and monitor residual risks throughout the project?
Answer: Risk register
The risk register is the primary document for tracking identified risks, responses, owners, and current status throughout the project lifecycle.
For a project including reforestation, Ray is the project manager. Ray seeks anonymous opinions from six experts while also sending out a questionnaire including dangers that have been discovered by the project team in order to boost the process of detecting risks. What method is Ray employing?
Answer: Delphi technique
The Delphi technique is a structured communication method used to gather expert opinions, often for risk identification or estimation. It involves sending out questionnaires to a panel of experts, collecting their anonymous responses, and then providing summarized feedback for subsequent rounds. This iterative process helps achieve consensus while minimizing bias and groupthink.
A previously identified risk has now occurred on the project. What does this risk become in project management terminology?
Answer: An issue
When a risk event actually occurs, it transitions from a risk (uncertain future event) to an issue (a current problem that requires immediate action).
To limit a team's work in progress and potentially reduce risks while balancing demand against the team's delivery throughout adaptive projects, an on-demand strategy based on the idea of constraints and pull-based scheduling concepts from lean manufacturing is known as:
Answer: Kanban System
The Kanban System is a lean manufacturing concept adapted for adaptive projects, focusing on visualizing work, limiting work in progress (WIP), and using a pull-based scheduling approach. This strategy helps balance demand with the team's delivery capacity, thereby reducing bottlenecks and risks. It directly addresses the need to limit WIP and improve flow in project management.
What is the purpose of a risk communication plan within a project?
Answer: To define who receives what risk information, when, and through which channel
A risk communication plan specifies the audience, frequency, format, and channel for each type of risk information to ensure consistent and appropriate reporting.
How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- pmi.org — Passing score, score release, test dates, renewal, fees, score validity, exam format, retake policy · verified Oct 2026
- pearsonvue.com — Test delivery · verified Oct 2026