Risk Monitoring and Control Flashcards

6 cards from real Project Risk Management practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 6 Risk Monitoring and Control flashcards as text
  1. A project manager is holding a recurring meeting with key stakeholders to discuss the current status of identified risks, the effectiveness of implemented responses, and to identify any new risks that have emerged. What is the primary purpose of this activity in the Monitor Risks process?

    Answer: To ensure risk responses are being executed as planned and to evaluate their effectiveness.

    This scenario describes a risk review meeting. The core purpose of such meetings within the Monitor Risks process is to track identified risks, monitor residual risks, identify new risks, and evaluate the effectiveness of risk response plans.

  2. A project manager commissions an external team to formally examine and document the effectiveness of the project's risk response planning and the execution of the overall risk management process. What tool or technique is being used?

    Answer: Risk Audit

    A risk audit is a formal, often independent, examination of the entire risk management process. Its purpose is to assess the effectiveness of risk management planning and response execution, not just the status of individual risks.

  3. Which of the following is a primary objective of performing a risk reassessment during the Monitor Risks process?

    Answer: To identify new risks, re-evaluate existing ones, and close outdated risks.

    Risk reassessment is a key activity in risk monitoring that involves regularly reviewing the risk register to identify any new risks, reassessing the probability and impact of current risks, and closing risks that are no longer relevant to the project.

  4. A project team implemented a mitigation strategy for a high-probability technical risk. During monitoring, performance data shows the risk's impact is actually increasing. What should be the project manager's immediate next step?

    Answer: Analyze the situation to determine why the response was ineffective and develop an alternative response plan.

    A key part of the Monitor Risks process is evaluating the effectiveness of implemented risk responses. If a response is not working, the team must analyze the situation, understand the cause, and develop a new or modified response, which could include implementing a fallback plan.

  5. During project execution, the project manager compares the amount of contingency reserves remaining to the amount of risk remaining in the project to determine if the remaining reserve is adequate. This is an example of what technique?

    Answer: Reserve Analysis

    Reserve analysis is used throughout the project to monitor the status of contingency and management reserves. It involves comparing the amount of remaining reserves to the amount of remaining risk to determine if the reserves are still sufficient.

  6. While monitoring project progress, a project manager learns that a key supplier for a non-critical component has just declared bankruptcy. This was not an identified risk. What is the MOST appropriate first action for the project manager to take?

    Answer: Add the new risk to the risk register and perform an analysis.

    When a new risk is identified during the Monitor Risks process, the standard procedure is to first add it to the risk register. Following this, the risk should be analyzed (qualitatively and/or quantitatively) to understand its characteristics, which will inform the development of an appropriate response strategy.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. pmi.org — Passing score, score release, test dates, renewal, fees, score validity, exam format, retake policy · verified Oct 2026
  2. pearsonvue.com — Test delivery · verified Oct 2026