  1. A project manager is facilitating a qualitative risk analysis workshop. The team has identified numerous risks and now needs to prioritize them for further analysis or response planning. Which of the following is the primary tool used for this purpose?

    Answer: Probability and Impact Matrix

    The Probability and Impact Matrix is a key tool in the Perform Qualitative Risk Analysis process. It is used to visually map and prioritize individual project risks based on their likelihood of occurrence and the potential effect on project objectives.

  2. During a project's qualitative risk analysis, the team assesses the quality of the data being used to evaluate the risks. They are examining the data's accuracy, reliability, and integrity to ensure the analysis is based on solid information. What technique is the team employing?

    Answer: Risk Data Quality Assessment

    A Risk Data Quality Assessment is a technique used to evaluate the degree to which the data about risks is accurate and reliable for risk management. It helps determine the level of confidence in the qualitative analysis results and identifies if better data is needed.

  3. A project manager is prioritizing risks and notes that one particular risk, while having a moderate probability and impact, requires a response much sooner than other, higher-rated risks. The time to implement a response is short, and warning signs indicate it may occur soon. This consideration of timing is known as:

    Answer: Risk Urgency Assessment

    Risk Urgency Assessment is a technique used to determine which risks require near-term responses. It considers factors like the time available to implement a response (proximity), warning signs (triggers), and the time-sensitivity of the risk's impact.

  4. Which of the following is a key objective of the Perform Qualitative Risk Analysis process?

    Answer: To prioritize identified individual project risks for subsequent analysis or action.

    The primary purpose of Perform Qualitative Risk Analysis is to prioritize risks by assessing their probability of occurrence and impact. This prioritization helps the team focus on the most critical risks, which may then undergo further quantitative analysis or have response plans developed.

  5. A project team is grouping identified risks based on their common sources, such as technical, external, organizational, and project management. This helps in understanding the project's exposure to different types of risks and can aid in developing more effective risk responses. What tool or technique are they using?

    Answer: Risk Categorization

    Risk Categorization involves organizing risks into groups based on their source or the project area they affect. This is often done using a Risk Breakdown Structure (RBS) and helps to identify concentrated areas of risk and common root causes.

  6. In the Perform Qualitative Risk Analysis process, which of the following is a primary input that contains the list of identified risks to be assessed?

    Answer: Risk Register

    The Risk Register is the main input for Perform Qualitative Risk Analysis, as it contains the initial list of risks identified during the Identify Risks process. This process then updates the risk register with prioritization information.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. pmi.org — Passing score, score release, test dates, renewal, fees, score validity, exam format, retake policy · verified Oct 2026
  2. pearsonvue.com — Test delivery · verified Oct 2026