You are utilizing the quantitative risk analysis methodology' interviewing method. Which of the ensuing assertions is accurate?
Answer: Subject matter experts will be interviewed, even if they are not part of the project team, and the information derived will be used in your estimated monetary value analysis.
Explanation: Interviewing subject-matter experts will help you gather the pertinent data; they are not required to be on the project team.
You inform your project team during a status meeting that your risk register is only as good as the steps you take to manage the risk. If you don't also implement the responses, simply finding and documenting them won't assist. The overall risk exposure can only be handled pro-actively if ______ expends the necessary amount of effort in putting the responses into practice. You are talking about:
Answer: Risk owners
Explanation: Monitoring the risks and putting a risk response plan in place are the responsibilities of designated risk owners. Owners of risk response and risk managers are not terminology from the PMBOK Guide.
What distinguishes a risk audit from a risk review in particular?
Answer: A risk review is the process of identifying new risks, reevaluating existing risks, and closing risks that are out of date. A risk audit investigates and documents the effectiveness of risk responses as well as the effectiveness of the risk management process.
Explanation: A risk audit investigates and records the effectiveness of risk solutions, whereas a risk reassessment involves the discovery of new risks, a reevaluation of ongoing risks, and the closure of risks that are no longer relevant (PMBOK Guide page 351). Because risk reassessment is also a tool and approach used in the Control Risks process.
A new telecommunications project that is entering its second phase has just been given to you by Global Telecom Inc. as its project manager. There seem to be a lot of risks associated with this endeavor, but no one has assessed them to determine the range of potential outcomes. Who would you recommend to lead the project?
Answer: Plan Risk Management
Explanation: The process of outlining how to carry out risk management tasks for a project and will include all facets of risk identification in such circumstances is known as plan risk management.
To limit a team's work in progress and potentially reduce risks while balancing demand against the team's delivery throughout adaptive projects, an on-demand strategy based on the idea of constraints and pull-based scheduling concepts from lean manufacturing is known as:
Answer: Kanban System
The Kanban System is a lean manufacturing concept adapted for adaptive projects, focusing on visualizing work, limiting work in progress (WIP), and using a pull-based scheduling approach. This strategy helps balance demand with the team's delivery capacity, thereby reducing bottlenecks and risks. It directly addresses the need to limit WIP and improve flow in project management.
Which of the following range estimates includes the LEAST risk, assuming that the range estimates' endpoints are +/- 3 sigma from the mean?
Answer: O=27 days, P=33 days, Most likely=30 days
A smaller range between the optimistic (O) and pessimistic (P) estimates, when centered around the most likely value, indicates less uncertainty and therefore less risk. In option A, the range is 33 - 27 = 6 days, which is the narrowest range among the choices provided. This implies a higher degree of confidence and predictability in the estimate, signifying the least risk.
The price of deciding on one project while rejecting another is referred to as:
Answer: Opportunity cost
Opportunity cost refers to the value of the next best alternative that was forgone when a particular decision was made. In project selection, if one project is chosen over another, the opportunity cost is the potential benefit or value that could have been realized from the rejected project. It highlights the trade-offs inherent in resource allocation.
How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- pmi.org — Passing score, score release, test dates, renewal, fees, score validity, exam format, retake policy · verified Oct 2026
- pearsonvue.com — Test delivery · verified Oct 2026