Contract & Procurement Risk Flashcards
7 cards from real Project Risk Management practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 7 Contract & Procurement Risk flashcards as text
Which elements are typically included in a procurement risk register?
Answer: Vendor performance history, contract terms risks, and supply chain vulnerabilities
A procurement risk register tracks risks specific to vendor relationships, including performance history, contractual obligations, and supply chain vulnerabilities.
What is the purpose of source selection criteria in project procurement?
Answer: To evaluate and rank vendor proposals objectively and consistently
Source selection criteria provide objective standards for evaluating vendor proposals, reducing the risk of biased or poor vendor selection decisions.
A project manager learns a key vendor is experiencing significant financial difficulties. Which risk response is most appropriate?
Answer: Develop a contingency plan including an alternative qualified vendor
Developing a contingency plan with an alternative vendor is a proactive response that ensures project continuity if the primary vendor becomes unable to deliver.
What does 'contract risk allocation' mean in project procurement management?
Answer: Assigning financial and performance responsibilities between the buyer and seller
Contract risk allocation defines which party bears specific risks, ensuring risks are assigned to the party best positioned to manage and absorb them.
Which procurement strategy best reduces the risk of schedule delays caused by vendor non-performance?
Answer: Including liquidated damages clauses tied to milestone dates
Liquidated damages clauses impose pre-defined financial penalties for schedule delays, creating a strong financial incentive for vendors to deliver on time.
In procurement risk management, what does a 'force majeure' clause address?
Answer: Excusing contract non-performance due to unforeseeable extraordinary events
A force majeure clause protects both parties from liability when extraordinary, unforeseeable events such as natural disasters or war prevent contract performance.
What is the primary risk to the buyer when using a time-and-materials (T&M) contract for a long-duration project?
Answer: The buyer assumes open-ended cost risk because total price is not fixed
In T&M contracts, the buyer pays for all hours worked and materials consumed, so cost risk rests entirely with the buyer unless a price ceiling is contractually specified.
How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- pmi.org — Passing score, score release, test dates, renewal, fees, score validity, exam format, retake policy · verified Oct 2026
- pearsonvue.com — Test delivery · verified Oct 2026