What does the Critical Path Method (CPM) determine in a project schedule?
-
A
The most expensive sequence of tasks in the project
-
B
The longest sequence of dependent activities that determines the minimum project duration
-
C
The tasks with the highest probability of delay
-
D
The sequence of activities requiring the most resources