What does a Schedule Performance Index (SPI) of 0.85 indicate?
-
A
The project is 15% under budget
-
B
The project is 15% ahead of schedule
-
C
The project is behind schedule — only 85% of planned work has been earned
-
D
The project has consumed 85% of its total float