What is the purpose of a project budget baseline?
-
A
To provide an approved time-phased spending plan used to measure and control cost performance
-
B
To list all approved vendors and their contract amounts
-
C
To set the maximum salary for project team members
-
D
To document historical costs from previous similar projects