PMI-ACP Agile Planning & Estimation Flashcards

6 cards from real PMI-ACP practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 6 PMI-ACP Agile Planning & Estimation flashcards as text
  1. A burndown chart in agile tracks which of the following?

    Answer: The remaining work versus time remaining in an iteration or release

    A burndown chart visualizes the amount of remaining work against the time remaining, helping teams track progress toward the sprint or release goal.

  2. What does the term 'backlog refinement' (also called grooming) refer to in agile?

    Answer: The ongoing process of reviewing, estimating, and prioritizing backlog items

    Backlog refinement is the activity of adding detail, estimates, and order to product backlog items to keep it ready for upcoming sprints.

  3. Which agile estimation technique groups user stories into broad size categories such as small, medium, large, and extra-large?

    Answer: T-shirt Sizing

    T-shirt sizing uses clothing size categories to quickly and relatively group user stories by effort without assigning numeric values.

  4. In agile planning, what is the purpose of the 'cone of uncertainty'?

    Answer: To show how estimates become more accurate as a project progresses

    The cone of uncertainty shows that early in a project, estimates have wide variance; as more is learned, the range of uncertainty narrows.

  5. Which metric measures the total amount of value delivered to customers over the life of an agile project?

    Answer: Net Present Value (NPV)

    Net Present Value (NPV) is a financial metric used in agile portfolio management to measure the overall value delivered by a project relative to its cost.

  6. What is the purpose of a 'Definition of Ready' (DoR) in agile planning?

    Answer: To establish criteria that a user story must meet before it can be taken into a sprint

    The Definition of Ready specifies the minimum criteria a user story must meet (e.g., estimated, clearly defined, testable) before the team can pull it into a sprint.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. pmi.org — Fees, renewal, late registration, passing score, retake fee, score release, test dates, score validity, test delivery, eligibility · verified Oct 2026