Professional Scrum Master Agile Product Management 5 — Questions and Answers
Question 1: Which of the following is a sign that a Product Owner is NOT effectively managing the Product Backlog?
- The backlog contains items at varying levels of detail
- The top items in the backlog are well-refined and ready for Sprint Planning
- The backlog has hundreds of items with no clear ordering or priority (Correct answer)
- The backlog is regularly updated after Sprint Reviews
Correct answer: The backlog has hundreds of items with no clear ordering or priority
An unordered backlog with hundreds of vague items indicates poor backlog management and makes effective Sprint Planning impossible.
Question 2: What is the purpose of acceptance criteria on a Product Backlog item?
- To define what the developers must do technically to implement the item
- To clarify the conditions under which the item will be considered complete from a business perspective (Correct answer)
- To estimate the story points for the item
- To assign ownership of the item to a specific developer
Correct answer: To clarify the conditions under which the item will be considered complete from a business perspective
Acceptance criteria define the business conditions that must be satisfied for an item to be considered done from the Product Owner's perspective.
Question 3: During Sprint Planning, the development team says they cannot commit to all the items the Product Owner selected. What should happen?
- The Scrum Master overrides the team and forces commitment
- The Product Owner and team negotiate scope until the team can commit to a realistic Sprint Goal (Correct answer)
- The Sprint is skipped until the team has enough capacity
- Management assigns mandatory targets to the team
Correct answer: The Product Owner and team negotiate scope until the team can commit to a realistic Sprint Goal
Sprint Planning is collaborative; the team and Product Owner negotiate to arrive at a realistic Sprint Goal the team can commit to.
Question 4: What does 'empiricism' mean in the context of Agile product management?
- Following a fixed process that has been proven to work in other companies
- Making product decisions based on evidence from actual work and outcomes (Correct answer)
- Using only quantitative data to make backlog decisions
- Delegating all decisions to domain experts
Correct answer: Making product decisions based on evidence from actual work and outcomes
Empiricism in Scrum means basing decisions on transparency, inspection, and adaptation grounded in real experience and data.
Question 5: A Product Owner is asked to add a competitor's feature to the backlog immediately. What should guide their response?
- Always match competitor features to remain competitive
- Evaluate whether the feature aligns with the product vision and delivers genuine value to users (Correct answer)
- Reject all competitor-inspired features to maintain product differentiation
- Add it to the Sprint immediately to show responsiveness
Correct answer: Evaluate whether the feature aligns with the product vision and delivers genuine value to users
A Product Owner should evaluate any requested feature—including competitor-inspired ones—against product vision and user value rather than reacting automatically.
Question 6: How does the Scrum framework help manage risk in product development?
- By locking requirements upfront and preventing changes
- Through frequent inspection and adaptation in short Sprints that surface risks early (Correct answer)
- By requiring risk assessments to be completed before each Sprint
- By assigning a dedicated risk manager to the Scrum Team
Correct answer: Through frequent inspection and adaptation in short Sprints that surface risks early
Short Sprints with frequent reviews surface risks early, allowing the team to adapt before issues become costly.
Question 7: Which statement BEST describes the relationship between the Product Owner and the development team regarding backlog items?
- The Product Owner writes all technical specifications for the team to implement
- The Product Owner communicates the 'what' and 'why'; the team decides the 'how' (Correct answer)
- The team is responsible for ordering the backlog based on technical ease
- The Product Owner and team must agree on every technical decision
Correct answer: The Product Owner communicates the 'what' and 'why'; the team decides the 'how'
The Product Owner owns the 'what' and 'why' of backlog items, while the development team decides how to implement them.
Which of the following is a sign that a Product Owner is NOT effectively managing the Product Backlog?