Professional Scrum Master Professional Scrum Master Artifacts and Commitments Questions and Answers 2 — Questions and Answers
Question 1: Which Scrum artifact is specifically designed to provide transparency of the work planned for the Sprint?
- Product Backlog
- Sprint Backlog (Correct answer)
- Increment
- Release Plan
Correct answer: Sprint Backlog
The Sprint Backlog makes visible all the work the Developers identify as necessary to meet the Sprint Goal.
Question 2: What is the commitment associated with the Product Backlog?
- Sprint Goal
- Definition of Done
- Product Goal (Correct answer)
- Acceptance Criteria
Correct answer: Product Goal
The Product Goal describes a future state of the product and serves as a long-term objective for the Scrum Team to plan against.
Question 3: A Scrum Team consistently delivers Increments that meet the Definition of Done, yet stakeholders remain dissatisfied with product direction. What artifact commitment should the Scrum Master help the team revisit?
- Definition of Done
- Sprint Goal
- Product Goal (Correct answer)
- Sprint Backlog
Correct answer: Product Goal
Stakeholder dissatisfaction with direction indicates the Product Goal may need refinement to better align with stakeholder expectations.
Question 4: When multiple Scrum Teams work on the same product, what must be true about the Definition of Done?
- Each team creates its own Definition of Done
- The Definition of Done must be the same for all teams (Correct answer)
- The Scrum Master decides the Definition of Done
- The Definition of Done is optional for scaling
Correct answer: The Definition of Done must be the same for all teams
When multiple Scrum Teams work on the same product, they must mutually define and comply with the same Definition of Done.
Question 5: During a Sprint, a Developer realizes that a Product Backlog item cannot meet the current Definition of Done. What should happen?
- Lower the Definition of Done for this Sprint only
- Include the item in the Increment with a note about reduced quality
- The item should not be considered part of the Increment (Correct answer)
- Ask the Product Owner to waive the Definition of Done
Correct answer: The item should not be considered part of the Increment
Any Product Backlog item that does not meet the Definition of Done cannot be released or presented at Sprint Review and must not be included in the Increment.
Question 6: How does the Sprint Goal function as a commitment within the Sprint Backlog?
- It limits which Product Backlog items can be selected
- It provides flexibility for Developers to negotiate scope while maintaining coherence (Correct answer)
- It prevents any changes to the Sprint Backlog during the Sprint
- It serves as a performance metric for individual Developers
Correct answer: It provides flexibility for Developers to negotiate scope while maintaining coherence
The Sprint Goal creates coherence and focus, allowing Developers to negotiate the scope of work within the Sprint while still delivering value.
Which Scrum artifact is specifically designed to provide transparency of the work planned for the Sprint?