A superintendent is coordinating a steel delivery that must arrive before erection begins. Which Procore tool links procurement milestones directly to schedule activities?
-
A
Observations log
-
B
Meetings minutes tracker
-
C
Procore Procurement integrated with Schedule tasks
-
D
Punch list template