When using Procore's Schedule tool, what does the 'critical path' highlight in a project schedule?
-
A
Tasks with the most assigned workers
-
B
The sequence of tasks that determines the minimum project duration
-
C
Tasks that exceed budget thresholds
-
D
Milestones approved by the owner