In Procore, when a subcontractor submits a Potential Change Order (PCO), what is the superintendent's primary responsibility?
-
A
Approve it immediately to avoid delays
-
B
Review scope, cost, and schedule impact before escalating to the project manager
-
C
Reject it and ask for a resubmission
-
D
Forward it directly to the owner without review