A GC superintendent receives a Procore RFI response that requires a change in work scope. What is the correct next step in Procore's workflow?
-
A
Close the RFI and proceed without further documentation
-
B
Link the RFI to a Potential Change Order to formally track the cost and schedule impact
-
C
Archive the RFI in a separate folder
-
D
Submit a new RFI to replace the original