A subcontractor submits a Notice of Delay via email outside of Procore. What should the superintendent do to maintain proper project records?
-
A
Ignore it since it was not submitted through Procore
-
B
Upload the email as an attachment to a Procore Correspondence or log entry
-
C
Respond only by phone
-
D
Delete the email after reading it