In Procore, what is the first step a superintendent typically takes when a change in scope is identified in the field?
-
A
Submit a change order directly to the owner
-
B
Create a Potential Change Order (PCO)
-
C
Issue a revised project schedule
-
D
Send an RFI to the architect