When tracking time and materials (T&M) work for a potential change order, what should a Procore superintendent document daily?
-
A
Equipment costs only, as they are the largest expense
-
B
Labor hours, material quantities, and equipment usage with supporting photos and receipts
-
C
Just the total estimated cost for the day
-
D
Only the subcontractor's daily invoice