What does a superintendent do when a subcontractor requests a change to their scope of work in Procore?
-
A
Evaluate the request, document it as a PCO, and issue a Commitment Change Order (CCO) once approved
-
B
Verbally authorize the change and update the schedule
-
C
Reject all scope changes to maintain the original contract
-
D
Move the change request to the punch list