How should a superintendent use Procore's submittal log during project closeout?
-
A
Verify that all required submittals have been approved and compile them into the operation and maintenance (O&M) manual for the owner
-
B
Delete unapproved submittals to clean up the log
-
C
Transfer all submittals to the punch list
-
D
Archive the submittal log without review