How should a superintendent manage punch list items in Procore to ensure timely completion before project closeout?
-
A
Set due dates, assign items to responsible parties, and use the punch list aging report to escalate overdue items
-
B
Create all punch list items on the last day of the project
-
C
Leave punch list items unassigned so anyone can fix them
-
D
Verbally communicate punch list items to subcontractors without logging them in Procore