Procore Superintendent Certification Procore Superintendent Document Control & RFIs 2 — Questions and Answers
Question 1: What does 'ball in court' mean on a Procore RFI?
- It identifies which party is currently responsible for responding (Correct answer)
- It marks the RFI as closed
- It assigns a cost to the RFI
- It links the RFI to a drawing
Correct answer: It identifies which party is currently responsible for responding
The 'ball in court' field identifies who currently holds responsibility for the next action on the RFI.
Question 2: Which Procore document control best practice helps a superintendent avoid working from outdated drawings?
- Always use the Drawings tool rather than downloading PDFs locally (Correct answer)
- Print all drawings at the start of the project
- Use the submittal log for drawing references
- Request physical drawing sets from the architect
Correct answer: Always use the Drawings tool rather than downloading PDFs locally
Using Procore's Drawings tool ensures the superintendent always views the latest revision since updates are reflected in real time.
Question 3: When logging documents in Procore, what is the benefit of linking an RFI to a specific drawing and specification section?
- It creates a direct traceability trail connecting the question to the relevant contract documents (Correct answer)
- It automatically generates a change order
- It notifies the owner of a dispute
- It closes the RFI automatically
Correct answer: It creates a direct traceability trail connecting the question to the relevant contract documents
Linking RFIs to drawings and spec sections creates traceability so anyone can quickly understand the context of the clarification.
Question 4: In Procore, what is the recommended way to mark an RFI as resolved?
- Change the RFI status to 'Closed' after a formal response has been received and distributed (Correct answer)
- Delete the RFI from the log
- Archive the RFI without responding
- Move the RFI to the punch list
Correct answer: Change the RFI status to 'Closed' after a formal response has been received and distributed
Closing an RFI with the formal response recorded ensures the record is complete and auditable for the project closeout.
Question 5: Why is it important for a superintendent to set a 'due date' when creating an RFI in Procore?
- It communicates urgency and helps the design team prioritize responses that affect active field work (Correct answer)
- It automatically bills the architect for delays
- It assigns a cost code to the RFI
- It schedules a daily log entry
Correct answer: It communicates urgency and helps the design team prioritize responses that affect active field work
Setting a due date signals urgency and helps prevent RFI delays that could stall construction activities.
Question 6: What is the benefit of attaching photos to an RFI in Procore?
- Photos provide clear visual context that helps the design team understand the field condition requiring clarification (Correct answer)
- Photos automatically generate a punch list item
- Photos close the RFI immediately
- Photos create a change order request
Correct answer: Photos provide clear visual context that helps the design team understand the field condition requiring clarification
Visual documentation through photos gives the design team a precise understanding of the existing condition, leading to faster and more accurate responses.
What does 'ball in court' mean on a Procore RFI?